Tracker · Pre-application
Apollo Atomics
The U.S. Nuclear Regulatory Commission (NRC) is currently engaged in pre-application activities with Apollo Atomics regarding a construction permit application.
- Who
- Apollo Atomics, Inc.
- Design
- Not stated
- Reactor type
- Other Designs/ Not Specified
- Status
- Active on the NRC index
- What
- Pre-application activities associated with a future construction permit application
- When
- April 2026 to present
- Site
- Not stated on the NRC page in this snapshot.
- NRC page reviewed
- Thursday, October 01, 2026
Dockets
Status timeline
Dates are printed as the NRC page prints them, including the actual (A) or target (T) mark.
The NRC page in this snapshot does not list a milestone table.
NRC activity table
| Product | Type | Reference | Status |
|---|---|---|---|
| Apollo Atomics Regulatory Engagement Plan | Regulatory Engagement Plan | ML26092A283 | No review requested |
| Quality Assurance Program Description | Topical Report | ML26261A083 | Under Review |
Related Federal Register notices
Included when a notice shares a docket printed on the NRC page, or when the notice title repeats the project or design name. Other NRC notices are left out.
No in-scope Federal Register notice is linked to this project.